(at 3.2 kms the Longest bridge in Australia)
90x prefabricated 23 metres long Headstock Cages
180x prefabricated Pier Columns
180x 23m long prefabricated Diaphragm beams
90x 40 tonne DECK pours – Total project 6000 tonnes/8 months production
All prefab units were built in engineered Jigs off site, and transported in purpose built cradles to site
Please click photos to enlarge
Substantial Pile Cap foundations, Prefabricated Piers, Insitu built headstocks (80 tonnes in two 9 hour shifts)
Large Deck pours – 10,000 tonnes – 12 months production time
Please click photos to enlarge
All CRCP pavements – double layer Seamless Bridge Approach pavement,
Bridge decks and 20 kms of reinforced foundation slab & barrier.
Average crew size 50 men placed 15000 tonnes in 12 months and won NSW work cover awards for best solution to a manual handling situation (2005)